Five Estuaries and North Falls Archaeology Surveys

Five Estuaries and North Falls are jointly carrying out archaeological trial trenching surveys starting in the week commencing the 8 September 2025. 

The works will be taking place within our proposed development boundary between Bentley Road and Ardleigh Road (as shown on the below plan), within the parish of Little Bentley, on private land in agreement with the relevant landowners.

Archaeological trial trenching involves the excavation of trial trenches across a site to estimate the archaeological potential.

The surveys will be taking place near Little Bromley 17 Public Right of Way; however, this will remain open throughout the works with fencing and signage as appropriate.  

This is the second stage of trial trenching following those that we undertook within the proposed substation area in 2023 and will continue next year at other areas along the proposed cable route. This is not the start of either of the project’s construction as we are still awaiting consenting decisions.  

The surveys are being carried out jointly by Five Estuaries and North Falls to help the projects understand the archaeology that is present to inform the next stage of mitigation, and whether any more detailed set piece excavations may be required (if significant archaeology is identified), which can be planned in prior to the main works starting. This approach is detailed in the Archaeological Mitigation Strategy: EN010115-001695-10.47 Archaeological Mitigation Strategy (AMS) – Revision B (Clean).pdf.

The locations of the trenches have been informed by using desk-based sources (such as aerial photography and existing records) and the geophysical surveys we carried out in 2023. The trenches target potential archaeology as well as blank areas to be explored.

The works are expected to take around six to eight weeks, being complete by mid-October, subject to weather conditions.

The works will be undertaken by our contractor Wessex Archaeology. The trenching will take place between 8am and 5pm Monday to Friday. All staff carparking will be located within the work area, or at offsite locations as agreed with landowners and designated accesses will be used. Equipment will be secured onsite when works are not taking place in agreement with the relevant landowners. The topsoil and subsoil will be segregated during the trenching, and the field will be fully reinstated on completion of the works.

Five Estuaries and North Falls onshore development boundary